Surat Metro Phase I

Two corridors totalling 40.35 km and 38 stations are being built across Surat.

Under constructionas of 31 March 2026
Elevated pillars for Surat Metro under construction
Elevated Surat Metro works in January 2026. · Nizil Shah · Wikimedia Commons · CC BY-SA 4.0 ↗

Overview

Phase I combines elevated and underground sections between Sarthana and DREAM City, and between Bhesan and Saroli. Current GMRC expenditure and active systems and integration tenders support an under-construction classification; no part is presented as operational.

Why this status

GMRC reported ₹8,751.76 crore of provisional expenditure by 31 March 2026 and continued issuing Phase I works tenders during 2026.

Verified facts

Network

40.35 km

Stations

38 — 32 elevated and 6 underground

Corridors

Sarthana–DREAM City and Bhesan–Saroli

Verified milestones

Project timeline

  1. 9 March 2019

    Phase I approved

    The two-corridor project received Government of India approval.

  2. 31 March 2026

    Construction spending continues

    GMRC reported provisional expenditure of ₹8,751.76 crore against the sanctioned project cost.